News & City27 Nov 20262 min read

Update: NH-44 Ramban-Banihal: Viaduct Due by 30 November, Two Tunnels Now Planned for the Third Week of December

NHAI details now put the Digdol-Khooni and Panthiyal tunnels in the third week of December, with the Nachlana-Kishtwari Pather viaduct due by 30 November.

JammuBeat Team

Update: NH-44 Ramban-Banihal: Viaduct Due by 30 November, Two Tunnels Now Planned for the Third Week of DecemberImage Source: Greater Kashmir

The story so far

The Jammu-Srinagar highway through Ramban has been the road students, jobseekers and winter travellers watch most closely. We have followed the works since the Digdol-Panthiyal tunnel's second tube neared completion (our 16 November report) and our weekend highway checklist.

What's new

Details from NHAI's Project Implementation Unit in Ramban, reported on 25-26 November, give firmer timelines:

  • Nachlana-Kishtwari Pather viaduct (1.15 km): construction complete, due to open by 30 November.

  • Digdol-Khooni nullah tunnel (2.6 km): excavation complete; protection works were expected to finish within days; opening planned for the third week of December.

  • Panthiyal parallel tunnel (650 m, beside the operational T-5 tunnel): construction complete and final laying under way; also planned for the third week of December.

NHAI officials said: “With the commissioning of both tunnels, commuters are expected to get four-lane connectivity from Digdol to Magarkote.” Ramban's Deputy Commissioner, Mohammad Alyas Khan, inspected the works, asked agencies to open the viaduct by month-end and to speed up the second tube of the Panthiyal tunnel, and asked for passenger sheds and toilets at designated points.

What to do differently

Treat all dates as targets, not promises: do not plan a trip around the tunnels opening on a given day. Check the latest traffic advisory before you drive, and expect disruptions to continue until the works are formally opened.

Sources