125 of 127 Projects and Rs 2,940 Crore: Jammu's Smart City Ledger, Read Properly

The Centre told the Rajya Sabha that Jammu has finished 125 of its 127 Smart City projects. Here is what that money actually built, and the two things still outstanding.

JammuBeat Team

125 of 127 Projects and Rs 2,940 Crore: Jammu's Smart City Ledger, Read ProperlyImage Source: varun Bajaj / Wikimedia Commons

Rs 2,940 crore. That is what the Union government told Parliament this month has been spent, and completed, on Smart City projects in Jammu — against a sanctioned Rs 2,969 crore. In project terms: 125 of 127 finished, with two left.

The figures came in a written reply in the Rajya Sabha by Tokhan Sahu, Minister of State for Housing and Urban Affairs, in the first week of August 2026. The data is as of 31 March 2026.

It is a large enough number to be meaningless on its own, so it is worth breaking down — because almost every part of central Jammu that a young resident uses on an ordinary day was paid for out of this line.

The numbers, in order of size

  • Jammu: 125 of 127 projects complete, Rs 2,940 crore of Rs 2,969 crore sanctioned.

  • Srinagar: 157 of 161 projects complete, Rs 3,532 crore of Rs 3,634 crore sanctioned.

  • J&K combined: 288 projects sanctioned at Rs 6,603 crore; 282 completed, worth Rs 6,472 crore; six still under implementation.

  • Nationally: 7,790 of 8,064 projects complete — about 97 per cent — worth Rs 1,56,257 crore against Rs 1,64,811 crore sanctioned.

So J&K's two smart cities are running slightly ahead of the national completion rate, at roughly 98 per cent against 97.

What Rs 2,940 crore actually bought

The parliamentary reply gives totals, not an itemised list. But the individual projects have been landing publicly through this year, and they are recognisable:

  • The Tawi riverfront, which has gone from an embankment to the city's default evening walk, complete with boating.

  • The Residency Road corridor — paver footpaths, rebuilt drains and cables put underground, at Rs 9.18 crore. (We walked it here.)

  • Tawi Wonderland at Bhagwati Nagar, the Rs 11-crore park built out of scrap, which opened on 6 August. (What it is actually like.)

  • The electric bus fleet, and the Rs 23.04-crore depot for 100 e-buses whose foundation stone was laid at Bhagwati Nagar on 6 August. (The depot story.)

Who actually spent it

One structural thing worth knowing, because it explains why "the government" is a slippery answer when something goes wrong. Smart City money was not spent by the municipal corporation. Each of the 100 cities in the mission set up a special purpose vehicle — a company — to hold the funds and award the contracts. In Jammu that company is Jammu Smart City Limited.

That is why the projects above are credited to JSCL rather than to JMC, and why several of them are run on public-private terms rather than departmentally. Tawi Wonderland is the clearest example: it was built with a private partner on a public-private arrangement, with that partner operating the park for a fixed term and sharing the earnings. The park is public infrastructure; the turnstile is a business.

None of that is unusual or improper — it is how the mission was designed nationally. But it changes who you complain to when a light stops working, and it means the maintenance question outlives the construction budget.

Jammu against Srinagar

The two cities are close to level on completion rate — Jammu 98.4 per cent of projects, Srinagar 97.5 per cent — but not on money. Srinagar was sanctioned Rs 3,634 crore against Jammu's Rs 2,969 crore, a gap of about Rs 665 crore, and had 161 projects to Jammu's 127.

That gap is not evidence of anything on its own; the two cities entered the mission in different rounds with different project mixes. It is simply the shape of the ledger, and it is the sort of number that tends to get asserted in argument without anyone checking it. The checked version is above.

The two that are left

Jammu's two outstanding projects were the Waste to Wonder park at Bhagwati Nagar and an oceanarium at Bagh-e-Bahu. The first of those opened on 6 August 2026, which means that as of this month Jammu is effectively down to one — the oceanarium, which has been reported as expected around the turn of 2026-27.

Worth being precise here: the parliamentary figures are frozen at 31 March 2026, so the park's opening in August is not yet reflected in the 125-of-127 count. The ledger is slightly better than the number in the reply.

The bit that gets skipped

The same reply recorded that no inquiry has been initiated into alleged financial irregularities or project mismanagement in either city, with delays attributed to procedural and logistical constraints. That is the government's position as stated to Parliament, and it is reported here as that — not as a finding either way.

It is also worth knowing that the Smart Cities Mission as a national programme formally concluded on 31 March 2025. What is being reported now is the tail: finishing what was already sanctioned, not new money arriving.

Why a 22-year-old in Jammu should care about a parliamentary answer

Because this is the closest thing to a receipt that exists. For most of the last five years the Smart City story in Jammu has been told one ribbon at a time — a footpath here, a park there, a bus route announced. A consolidated figure lets you ask a different and more useful question: the mission is over, the money is 98 per cent spent, and the visible city is what it bought. Is the riverfront maintained in three years? Do the e-buses still run to schedule once the depot opens? Does the oceanarium arrive?

Those are the questions that decide whether Rs 2,940 crore was infrastructure or scenery, and they get answered after the headlines stop.

Sources: Rajya Sabha reply by Tokhan Sahu, Minister of State for Housing and Urban Affairs, August 2026, as reported by Elets Smart City and Kashmir Life.